2024 Mill & Overlay and Smithtown Road Drainage Improvements

Overview

The City of Shorewood authorized the preparation of plans and specification of the 2024 Mill & Overlay and the Smithtown Road Drainage Improvements project in January 2024. The project is identified in the Capital Improvement Plan (PDF) for maintaining and extending the longevity of the existing roadway infrastructure throughout the city. The Mill & Overlay Project includes streets that have poor pavement ratings and/or are carryovers from previous projects in which they were cut due to budget.  The Smithtown Road Drainage Improvements Project is addressing several drainage issues along its length. 

The following roadways are included in the mill and overlay project. Project work will be completed in 3 phases. View phasing map (PDF)

  • Phase 1: Bracketts Road, Chestnut Court, Maple Street, Oakview Court, Whitney Circle
  • Phase 2: Boulder Circle, Spruce Hill Court, and instersections off Smithtown Road: Howard's Point Rd, Fairway Dr, Ayrshire Ln, Star Ln, Christopher Rd
  • Phase 3: Church Road, Murray Street/Court, Lilac Lane, Smithtown Road and Boulder Circle intersection, Smithtown Road and Cajed Lane intersection, and the miscellaneous utility improvements on Eureka Road.

Project Timeline & Work Scope

Mill and overlay work will be done in 3 phases. The above list outlines which streets are included in each phase. See updates below for the latest schedule information. Please note, schedule is subject to change due to weather.